~TSTEP

 

~TSTEP, NPHASE, EntTyp, ENTNUM, STATUS, DELAY

Defines the excavation or construction phases of the tunnel.

PREP7: GEOTECHNICAL MODULE: Tunnels

NPHASE

Phase number.

EntTyp

Entity type.

AREA or 1

Area                

LINE or 2

Line

ENTNUM

Entity number.

STATUS

Status of the phase.

0

Excavate        

1

Construct

DELAY

Delayed time of the phase respect to the successive advances.

0

Starts at the current advance

n

Starts at the advance n